Jump to content

Taxpayers to dig for £20M for Liverpool Dock


Non-Believer

Recommended Posts

7 minutes ago, Kopek said:

We're stuck with it, aren't we?

If IOMG doesn’t pay or Tynpotwald doesn’t authorise additional monies, then it will take longer to complete, or may never be completed. Think of the repercussions, the reputational damage to the island. Sadly this is one huge mess from start to finish and a permanent memorial to political incompetence, and vain posturing by the ruling elite.

  • Like 4
Link to comment
Share on other sites

53 minutes ago, Kopek said:

If there were get out clauses, then perhaps, in the early days they could have been used, still a loss but not as much as the overall cost!!! But someone would have had to admit to a mistake?

However, Liverpools requirement for a 'cruise ship berth' still meant we would ahve lost the old Manx berth?

Doesn't seem like the cruise ship berth is going to happen???

You can cancel the contract. At your peril. No pay, no terminal or just part of one  the contractor would stop work and start the path to litigation. 

If the project manager deems you have to make a payment, you have to make a payment. 

Link to comment
Share on other sites

1 hour ago, Happier diner said:

We have discussed this before. These contracts have no such limitations. Termination yes. Break clauses no. 

We have and I still cannot understand how we have got ourselves into a contract where there is no option but continue paying even if the nature of the work undertaken varies so much that it is costing 4 times that originally envisaged.  

Not sure how termination differs from a break clause really.  

 

Link to comment
Share on other sites

28 minutes ago, Gladys said:

We have and I still cannot understand how we have got ourselves into a contract where there is no option but continue paying even if the nature of the work undertaken varies so much that it is costing 4 times that originally envisaged.  

Not sure how termination differs from a break clause really.  

 

Classic case of their lawyers being better than IOMG lawyers. 

Link to comment
Share on other sites

1 hour ago, Amadeus said:

Classic case of their lawyers being better than IOMG lawyers. 

No lawyers are involved. No one has sued anyone yet. The most obvious legal action would be IOMG vs the designer. That may well happen yet. This would be an allegation of negligence. 

Link to comment
Share on other sites

Many of the problems appear to have arisen from difficulties with the nature of the ground in the location. The building itself is a new steel frame structure which should have presented no problems bar material price increases.

It is my understanding that IoMG were well forewarned of these ground problems but that aside, whoever did the surveying should have picked up on these characteristics, to include the UXO, and flagged it up.

Unless of course they did but IoMG were just too confident in their own knowledge and expertise to take any heed. I would personally have more faith in Lars Ugland's appraisal of the situation than anything issuing from the DOI.

  • Like 5
Link to comment
Share on other sites

22 minutes ago, Non-Believer said:

Many of the problems appear to have arisen from difficulties with the nature of the ground in the location. The building itself is a new steel frame structure which should have presented no problems bar material price increases.

It is my understanding that IoMG were well forewarned of these ground problems but that aside, whoever did the surveying should have picked up on these characteristics, to include the UXO, and flagged it up.

Unless of course they did but IoMG were just too confident in their own knowledge and expertise to take any heed. I would personally have more faith in Lars Ugland's appraisal of the situation than anything issuing from the DOI.

That is very possible the main issue. Combined together contributing to the massive outturn cost we have. 

1. Ridiculous under estimated at the start.

2. Poor or even lack of initial investigation

3. No consideration of the scout of the thrusters and subsequent change if scope and specifications.

4. COVID

5. General underperforming of all involved. 

Edited by Happier diner
Link to comment
Share on other sites

1 hour ago, Non-Believer said:

Many of the problems appear to have arisen from difficulties with the nature of the ground in the location. The building itself is a new steel frame structure which should have presented no problems bar material price increases.

It is my understanding that IoMG were well forewarned of these ground problems but that aside, whoever did the surveying should have picked up on these characteristics, to include the UXO, and flagged it up.

Unless of course they did but IoMG were just too confident in their own knowledge and expertise to take any heed. I would personally have more faith in Lars Ugland's appraisal of the situation than anything issuing from the DOI.

what ground problems exactly ?  

 

Link to comment
Share on other sites

49 minutes ago, Happier diner said:

That is very possible the main issue. Combined together contributing to the massive outturn cost we have. 

1. Ridiculous under estimated at the start.

2. Poor or even lack of initial investigation

3. No consideration of the scout of the thrusters and subsequent change if scope and specifications.

4. COVID

5. General underperforming of all involved. 

No. 2 - 110% insufficient site investigation, I don't think even ground radar was used to determine the substructure or lack thereof. 

I also think there was an element of pressure from either or both Peel Ports and Liverpool Council to free up the existing landing stage area for further development of the cruse terminal, which I believe is not now going to happen (or indeed if it was ever a real consideration)!

  • Like 1
Link to comment
Share on other sites

34 minutes ago, WTF said:

what ground problems exactly ?  

 

Run up to last election, Lawrie Hooper told me that Peel Ports had had their own surveys done on the site in the past and had found it to be fraught with potential difficulties in nature.

Hooper didn't expand on that but he did say that it was flagged up to DOI during lease/purchase negotiations, ie they knew full well about it. It was one of the reasons behind Peel's proposal to construct the berth they offered marginally further out the estuary rather than at Half Tide, they didn't want to get involved there.

The proposed location wasn't acceptable to our powers-that-be so the decision was made to go it alone at Half Tide.

Obviously things have come to pass that would appear to have vindicated Peel's outlook on the matter.

Edited by Non-Believer
typo
  • Like 2
Link to comment
Share on other sites

It’s the same story as the Prom.

The DOI jettisoned their construction specialists to reduce headcount.

The DOI then hired in clueless consultants who come up with a stratospherically shit design.

The DOI plough on with the shit design, despite everyone saying it’s a shit design, because obviously the clueless consultants know best.

The DOI then spends a fortune on remediation work for the shit design. The clueless consultants blame the DOI for “changing the brief”, even though the brief hasn’t changed, it’s just the initial design was shit.

  • Thanks 1
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...